Nano Nuclear Energy announced that the U.S. Nuclear Regulatory Commission (NRC) has begun its formal review of the Construction Permit Application (CPA) for the deployment of its KRONOS MMR™ microreactor at the University of Illinois Urbana-Champaign. This marks a significant milestone in the regulatory process, moving the project closer to licensing and construction.

Key Details

  • Project: Deployment of the KRONOS MMR™ Energy System at the University of Illinois Urbana-Champaign.
  • Regulatory Milestone: The NRC has officially initiated its formal environmental, safety, and technical review process following the CPA's acceptance on May 18, 2026.
  • Projected Timeline: The NRC's environmental assessment is expected by Spring 2027 and the safety evaluation by early Fall 2027, potentially allowing for initial construction activities to begin in the second half of 2027.