Shares of Cipher Digital jumped 7.3% to $16.29 Wednesday morning after the former Bitcoin miner announced it has begun building natural-gas lateral pipelines capable of powering up to 2.5 gigawatts of onsite electricity generation — enough to run roughly two million homes — across multiple data-center sites. The move is an aggressive attempt to sidestep the very problem choking AI-infrastructure growth nationwide: getting power from the grid.

• Bringing Your Own Power Plant Sidesteps the Biggest Bottleneck in AI

The lateral pipelines will connect Cipher's sites to nearby natural gas supplies, enabling on-site generation of up to 2.5 GW of electricity.

Cipher will work with power providers to develop and operate generation infrastructure at these sites, and building the lateral pipelines is a significant step toward making new power available to the sites before the end of 2027. For context, Cipher's grid pipeline alone targets approximately 5.3 GW of total portfolio capacity by 2030+ , so adding 2.5 GW off-grid could nearly double the company's power footprint — if it can actually deliver.

• The $11.4 Billion Backlog Anchors the Bull Case, But Execution Risk Is Real

Future revenue growth is anchored by approximately $11.4 billion in contracted revenue over initial lease terms of 10 to 15 years.

The bear case is that execution risk, construction delays, and power delivery uncertainty reduce the realized value of those contracts materially. Building pipelines, securing gas supply agreements, and constructing generation facilities simultaneously introduces significant engineering and financing complexity, as management acknowledged significant engineering and financing complexities as recently as Q1.

• The Bitcoin Exit Is Nearly Complete — This Is Now a Data-Center Landlord Story

The company plans to fully wind down Bitcoin mining operations by July 2027 at the latest, potentially repurposing the Odessa site for high-performance computing.

The company is not providing AI compute services, instead acting as a power shell lessor, avoiding GPU risk but limiting upside to real estate-like returns. That means Cipher's ceiling is set by how many megawatts it can deliver and lease, not by the AI chips inside.

• A 7% Pop Prices In Optimism — But the Hard Work Hasn't Started

The company projects contracted capacity to generate approximately $793 million of average annualized net operating income over the base lease terms. Today's announcement adds no new tenants and no new revenue yet. Cipher disclosed an amendment to its Black Pearl campus lease, accelerating the development timeline, and began delivering data center capacity at the beginning of August, two months ahead of the original schedule — a credibility boost. But 2.5 GW of gas-fired generation by late 2027 is an enormously ambitious timeline that investors should track quarter by quarter.